Relocate Your
Modular or Manufactured
Home Unit From Your Trailer Park To Your Own Rural Or City Lot! |
|
Superior Wood
foundations Provides complete
manufactured home relocation service including our guaranteed PWF
Basement or
Crawlspace Foundation. |
Below is a
typical project budget. Line by line items would be
corrected per actual cost, as every relocation project is
unique. |
|
28' X 70' Double Wide |
Rural
Site |
City
Lot |
|
|
|
Permits, sewer &
Water Tap Fees |
$
1,000 |
$
6,000 |
Septic And Well or
Sewer and Water Lines |
8,000 |
1,400 |
200 Amp Exterior
Electric Disconnect & Service Entrance |
1,500 |
1,500 |
Wire Well Pump |
200 |
N/A |
Re-Connect Plumbing,
Install Gas & Sewer Line |
1,500 |
1,500 |
12' Wide Gravel Drive
(City, 50 ft, Rural, 100 ft. with Culvert) |
1,500 |
500 |
Electric and Gas
Services |
500 |
200 |
Foundation Excavation,
Stone Base & Backfill |
1,595 |
1,595 |
4'6" Permanent
Wood Crawlspace Foundation |
4,700 |
4,700 |
Steel Beam And Column
Package |
2,200 |
2,200 |
Re-Locate Unit (Within
40 Miles, No Interior Finish Repair) |
5,200 |
5,200 |
Bulldozer Escort of
Unit (1 Day) |
450 |
450 |
General Conditions,
Debris Removal (1-20 Yard Dumpster) |
2,375 |
2,375 |
Sub Total |
$
30,720 |
$
27,620 |
12% Project Management
Fee |
3,686 |
3314 |
Total Estimated Cost of
Project |
$
34,406 |
$
30,904 |
|
|
|
For 9' high
Permanent Wood Foundation Basement with 4"
concrete floor add $ 16,500 |
Standard Terms are 35%
Down, 35% When Unit is in place, 30% Upon
Completion |
Other terms are
Negotiable With Customers Finance Company. |
Customer Participation
in Selection of Sub-Contractors and
"Hands-On" Performance of Mechanical
And/Or Miscellaneous Work Is Encouraged. |
Management Fee Will Be
Reduced to 8% on Sub-Contractors Hired Directly
by The Homeowner, And 4% on Work Performed By The
Homeowner. |
No Allowance For Finish
Grading, Topsoil, Lawn or Landscaping is
Included. |
|
For
additional information please or
call
(248) 634-8603 Fax (248)
634-8605 |
|
|
|