Recent Full Panel Installation Project | |
Basement
excavated, base P-rock placed. |
|
Day number
1 Footer plates in place. Setting First Panel. |
|
Setting Panels. | |
Panels
complete in 2 1/2 hours. |
|
Day
No. 2 Framing first floor. |
|
First floor is sheeted. | |
Treated
wood Basement floor. |
|
Rock
slips in place, ready for backfill. |
|
Day
No. 3 Setting wall panels. |
|
Panels
complete, setting gable ends. |
|
Day
No. 4 Roof trusses in place. |
|
Roof
sheeted, Shell complete. |