Recent Full Panel Installation Project | |
![]() |
Basement
excavated, base P-rock placed. |
![]() |
Day number
1 Footer plates in place. Setting First Panel. |
![]() |
Setting Panels. |
![]() |
Panels
complete in 2 1/2 hours. |
![]() |
Day
No. 2 Framing first floor. |
![]() |
First floor is sheeted. |
![]() |
Treated
wood Basement floor. |
![]() |
Rock
slips in place, ready for backfill. |
![]() |
Day
No. 3 Setting wall panels. |
![]() |
Panels
complete, setting gable ends. |
![]() |
Day
No. 4 Roof trusses in place. |
![]() |
Roof
sheeted, Shell complete. |