Recent Full Panel Installation Project
   
  Basement excavated,
base P-rock placed.
   
  Day number 1
Footer plates in place.
Setting First Panel.
 
   
  Setting Panels. 
   
  Panels complete in
2 1/2 hours.
   
Day No. 2
Framing first floor.
 
   
First floor is sheeted.   
   
Treated wood 
Basement floor.
 
   
Rock slips in place,
ready for backfill.
 
   
Day No. 3
Setting wall panels.
 
Panels complete,
setting gable ends.
Day No. 4
Roof trusses in place.
Roof sheeted,
Shell complete.